Borehole water to supplement NMB potable water supply

Published: September 14, 2021

<< BACK TO NEWS
The Nelson Mandela Bay Municipality’s drought mitigation plans are progressing well, with the construction of boreholes in Port Elizabeth currently underway. 
 
During an oversite visit on Tuesday, NMBM Mayoral Committee Member for Infrastructure and Engineering, Cllr Thsonono Buyeye expressed satisfaction with the progress made so far at the St George’s Park and Moregrove Wellfields where water will be extracted from boreholes, treated and distributed into the City’s bulk water system.
 
MMC Buyeye said it was important for residents to know that mitigation work to the severe drought crisis were underway however the cooperation of residents and businesses was equally as important as the mitigation plans were still under construction phases.
 
"We are happy with the progress so far, these projects started in July and it really gives us hope to see our bold plans becoming a reality. Through these projects we will be assisting our dams that are currently very low with the total dam levels currently sitting at 12.37%. In St George’s we are constructing four boreholes, these will be supported by the treatment works that is already at the site and the pump station we are also building on the site.”
 
"We are looking at producing a total of 3 million litres of water in St George’s Park once the project is done. The water from the boreholes will be pumped directly into the Churchill pipeline in order to feed other reservoirs at a high risk of running empty and this will reduce abstraction from the severely stressed western dams, that way preserving the little water that is left and developing a sustainable water supply resource for the future,” said MMC Buyeye.
 
The work underway at both Wellfields includes:
- Bulk earthwork and trenching
Construction of a treatment work and discharge pipework
Installation of mechanical and electrical equipment;
- Construction of secured chambers and equipping of boreholes;
- Installation of a collector pipeline to convey groundwater to a centralised point and;
- Construction of a pump station and pressurised pipeline.
 
The St George’s Park Wellfield project is expected to be completed in August 2022, while the Moregrove Wellfield is expected to be completed in May 2022, weather permitting.
 

"The Moregrove Wellfields include the Fort Nottingham, Glendinning and Fairview Wellfields located within the suburbs of Glendinningvale, Millard and Adcockvale respectively. A total of 10 production boreholes have been identified for this Wellfield project with combined pumping yield of between 2.5 and 4.2 million litres a day. We will treat and blend the water before it goes to the reservoirs,” Buyeye added.
 
A total of R160 million has been invested by the City for both projects.
 
Ends.
 
Issued by the Nelson Mandela Bay Municipality Communications Office.

Top stories


NMBM READY FOR SUMMER CUSTOMARY INITIATION SEASON November 12, 2026 Following the successful training of Traditional Surgeons and Assistants (Iingcibi namaKhankatha) organised by the Nelson Mandela Bay Municipality Initiation Forum, in collaboration with the Department of Health, the Nelson Mandela Bay Municipality...
POLITICAL PARTIES URGED TO REMOVE 2026 LOCAL GOVERNMENT ELECTION POSTERS November 12, 2026 The Nelson Mandela Bay Municipality is calling on all political parties and independent candidates who contested the 2026 Local Government Elections to remove all their election campaign posters and related election material from public spaces acro...
 

 

Using a Touch Screen?
Click below for instructions to fix Touch/Swipe issues experienced in Microsoft Edge.

Show me the fix! No thanks
This might take a while depending on your connectivity.
Please be patient while we search the entire site & all its modules for you...